DOWNTOWN
I-71 between Lytle Tunnel and Mount Adams Pedestrian Bridge: Periodic overnight lane and ramp closures may take place through fall 2018 as crews finish last parts of the rehab projects for the Lytle Tunnel and interstate bridge decks.
CENTRAL BUSINESS DISTRICT
Fourth & Race Mixed-Use Tower: Curb lane and sidewalk closed around construction site along Fourth Street, including mid block on Elm and Race streets between Fifth and Fourth for demolition through Nov. 30, 2018.
Columbia Square Streetscape: Curb lane and sidewalk closed mid block on Fifth between Main and Sycamore and mid block on Sycamore between Fifth and Sixth.
Fourth and Main: The sidewalk and curb lane adjacent to the Federal Reserve Bank building are closed until late November for streetscape upgrades.
Fiber Optic Cable Network: Expect short-term lane closures this week on the following street and intersections as crews install cable through underground conduit and repave areas where trench was dug:
- Broadway from Second to Fifth: Paving scheduled for Nov. 1 & 2
- Merhring Way from Central Avenue to Broadway
- Second Street from Central Avenue to Broadway
- Third Street from Central Avenue to Broadway
Fifth Street at Walnut: Lane closure to mid block on Walnut south of Fifth for demolition at site of new hotel.
Walnut between Eighth and Ninth and West Half of Eighth Between Main and Walnut: Curb lane restrictions for streetscape and sidewalk improvements.
Kroger Store Construction: Curb lane and sidewalk closed around construction site through September 2019. Includes:
- East side of Walnut between Court and Central Pkwy
- South side of Central Pkwy, west half of block between Walnut and Main
- North side of Court, west half of block between Walnut and Main
Fourth Street at Sycamore: Sidewalk closed for renovations to building at Eighth E. Fourth St.
Sycamore between Fourth and Fifth: Daily lane restrictions for building renovation
LYTLE PARK
Lytle Street between Pike Street and West Terminus: Closed for repairs to Lytle Tunnel. The east half of Lytle Park (above the tunnel) also is closed during the repairs and reconstruction.
OVER-THE-RHINE
Duke Energy Electric Upgrade Project: Charles Street closed between Central Avenue and Plum Street until mid December 2018. Curb lane closed on Central Avenue. Local traffic allowed.
Greater Cincinnati Water Works Main Replacement: Intermittent lane restrictions through fall 2018 at the following locations:
- Clay Street between Central Parkway and Liberty Street
- Thirteenth between Race and Main
- Fourteenth between Vine and Main Street
- Main Street between Orchard and Liberty Street
Elm Street between 14th and Odeon: Daily lane and sidewalk restrictions for Duke Energy pole replacement.
14th Street between Vine and Walnut: Daily lane restrictions for building renovation.