Construction Management Project Update For Mid May 2017

May 08, 2017

                                  CONSTRUCTION MANAGEMENT PROJECT UPDATE

May 7, 2017 – May 20, 2017

 

  1. Eggleston Avenue Shared Use Path

Engineer/Inspector: Sarah Perrino/Dave West

Contractor: Adleta Construction

 

Project Description:

This contract includes construction of a bicycle-pedestrian shared use path; installing new inlets; construction of a segmental wall; relocation of light poles and relocation of an irrigation control box.It also includes parking space removals and additions to an existing parking lot; landscaping including installation of tree lawns and plantings in a traffic island and roadway work including realigned curb returns, new curbs, new curb ramps, new drives, new pavement markings, new traffic control poles and devices, and traffic control signage.

                   Project Completion: 

             June 2017

 

              Community:

      Downtown

 

       Scheduled Activities for 5/7/2017 – 5/20/2017

  • Traffic signal work at Eggleston & Reedy Street
  • Fence installation
  • Project cleanup

               Maintenance of Traffic update for 5/7/2017 – 5/20/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times
  • During all non-working hours the streets shall be open and available for the movement of traffic
  • Single lane closure on Eggleston from 7:30am to 5:30pm south of Reedy Street

 

2.  Hillside Avenue at Tyler Street Landslide Stabilization

Engineer/Inspector: Mike Mann/Doug Dornette

Contractor: Ford Development Corp

 

Project Description:

This project includes landslide stabilization west of Tyler Street and involves 61 reinforced drilled piers with 59 plugs.

 

 

Project Completion Date:

June 2017

 

Community:

 Riverside

 

Scheduled Activities for 5/7/2016 – 5/20/2017

  • Embankment fill
  • Completion of grading
  • Begin curb work
  • Begin reconstructing of Tyler Street and Hillside Avenue

Maintenance of Traffic for 5/7/2016 – 5/20/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

 

 

3.  Marburg Avenue Bridge

  Engineer/Inspector: Mike Mann/Jay Brielmaier

  Contractor: John R. Jurgensen Co.

 

  Project Description:

  This project replaces the Marburg Avenue bridge over the Norfolk Southern Railroad.         The existing bridge will be removed and replaced.  The 86-year-old bridge connects 

  densely populated residential and commercial areas in Hyde Park and Oakley.

 

   Project Completion Date: 

          October 2017

 

   Community:

   Hyde Park, Oakley

 

   Scheduled Activities for 5/7/2016 – 5/20/2017

  • Continue construction on the substructure of the bridge
  • Continue pouring the footings, walls and piers.

                Maintenance of Traffic 5/7/2016 – 5/20/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

                                 

       4.  West MLK Improvements

              Engineer/Inspector: Don Stiens/Kevin Feldkamp/Dennis Winningham

              Contractor: John R. Jurgensen Co.

 

             Project Description:

 This project consists of 0.83 miles of roadway improvements to West Martin                        

 Luther King Jr. Drive from east of West McMicken Avenue to east of Clifton   

 Avenue, full depth pavement replacement (shift to north and widen), signal   

 upgrades and a 12’ multi-use path.

 

           Project Completion:

                     September 2017

 

                   Community:

                     Corryville        

 

                   Scheduled Activities for 5/7/2017 – 5/20/2017:

  •   Duke Energy installing new poles on the south side of MLK between Dixmyth and Hopple Street overpass

                   Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  •     Access for emergency vehicles, residents and businesses will be  maintained at all times.
  •     Traffic will be restricted to one lane in each direction

 

 

               

         5.           Northside Arterial Improvements

            Engineer/Inspector: Lisa Rowell/David Padur                                

             Contractor: Prus Construction

 

            Project Description:

            The project involves restructuring Colerain Avenue, Blue Rock and Elmore.  Elmore    

          between Dooley-By Pass and Colerain will become a two way traffic street when

          complete.  The listed streets will receive new curbs and sidewalks with a grass strip

          between the curb and walks.  All intersections within the project will receive new signal

          configurations.  The project also includes new asphalt pavement after concrete work is                       complete.

 

          Project Completion:

            May 2017

 

          Community:

            Northside

 

          Scheduled Activities for 5/7/2017 – 5/20/2017:

  • Punch list items

          Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

 

        6.  Ida Street Bridge Phase II

             Engineer/Inspector: Lisa Rowell/Bob Backscheider

             Contractor: Prus Construction

 

              Project Description:

The project involves demolition of dilapidated concrete on the substructure on the               bridge.  The deteriorated areas will be removed and replaced creating a more              substantial life expectancy for the bridge.  After the area receives repairs, the entire  

             bridge will be coated.

 

              Project Completion:

               October 2017

 

              Community:

               Mt. Adams

 

              Scheduled Activities for 5/7/2017 – 5/20/2017:

  • Sounding bridge piers, spandrels and beams
  • Removing deteriorated areas of concrete on bridge
  • Concrete pour on pier, spandrels and beams

              Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

 

 

        7.  Colerain Avenue (SCIP)

              Engineer/Inspector: Lisa Rowell/Brian Hurd

              Contractor: John R. Jurgensen Company

 

         

              Project Description:

 This project involves street rehabilitation on city streets.  Including full depth repairs,                           curb and curb ramps, asphalt surfacing and driveway aprons.  A retaining wall will also           be installed on the project.

 

Project Completion:

September 2017

 

Community:

Mt. Airy, Northside

 

Scheduled Activities for 5/7/2017 – 5/20/2017:

  • Concrete curb replacement
  • Concrete curb ramp replacement
  • Retaining wall installation

             Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

 

        8.         Street Rehab/Construction Services/Prus/2017

            Engineer/Inspector: David Krusling/Tony Baker/Bob Herling/Frank Mertz

            Contractor: Prus Construction Company

 

           

            Project Description:          

            This project includes planning the existing asphalt course as necessary; performing

          Partial and full-depth pavement repairs; placing an intermediate course of asphalt

          Where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk

          And driveway aprons where necessary; perfoming inlet adsustments; adjusting utility

          Castings to grade; resurfacing the entire pavement with asphaltic concrete; performing

          The necessary pavement markings work; removing and replacing traffic signage; and

          Replacing traffic loop detectors where applicable.

 

          Project Completion:          

            November 2017

 

          Community:

            Evanston and Oakley

 

          Scheduled Activities for 5/7/2017 – 5/20/2017:

  • Concrete curb and driveway installations
  • Full depth pavement repair
  • Partial depth pavement repair
  • Grind streets
  • Place leveling asphalt course

Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  • Access for emergency vehicles, residents, and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

 

 

       9.          Street Rehab/Construction Services/Adleta/2017

            Engineer/Inspector: Lisa Rowell/Emily Hunley/Nick Schinaman

            Contractor: Adleta Inc.

 

           

            Project Description:

            This project involves street rehabilitation on several city streets. Including full depth

          Repair, curb and curb ramps, asphalt surfacing and driveway aprons.  Casting

          Adjustments and pavement rejuvenation will also take place.

 

          Project Completion:

            October 2017

 

          Communities:

            Carthage, East Westwood, English Woods, Hartwell, North Avondale, Over-The-Rhine,          West End

 

          Scheduled Activities for 5/7/2017 – 5/20/2017:

  • Full depth repairs
  • Milling street and installing asphalt
  • Concrete curb installation
  • Concrete ramp installation

Maintenance of Traffic for 5/7/2017 – 5/20/2017:

  • Access for emergency vehicles, residents, and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

Share Article: