CINCINNATI – Since the November 1 fire at the southbound approach to the I-471/Daniel Carter Beard Bridge, there have been hundreds of people and dozens of companies involved in the Ohio Department of Transportation’s efforts to restore the structure that connects downtown Cincinnati to Newport, Ky. Here are the latest updates from ODOT, Kentucky Transportation Cabinet (KYTC), and the city of Cincinnati.
Demolition Progresses
Crews have removed the damaged sections of concrete bridge deck. Now, the attention turns to removing the damaged steel girders. A 550-ton crane has arrived on site from Nashville, Tennessee. There are nine truckloads of parts needed to assemble the crane. It will be used to remove the damaged girders as they are disassembled. Girder removal could begin as early as today. Crews will be watching the weather forecast. If winds are too strong, girder removal will have to be rescheduled.
Components Starting to Arrive
Bronze bearings, custom-fabricated in Brunswick, Ohio, have arrived at Great Lakes Construction’s office in Cincinnati after being expedited by the manufacturer. These will be used to put four of the new custom-fabricated girders on once they arrive from Bowling Green, Kentucky in mid-January.
Shoring Towers Relocated
A group of shoring towers has been moved south from their original location. These will support the remaining girders once the damaged girders are removed. There are a total of ten shoring towers supporting the structure during the next phase of demolition. These towers will remain in place through construction as well.
Northbound I-471 Wall Repair
Crews plan to begin pouring concrete to replace a 70’ damaged section of wall on the northbound side this week, weather permitting. All lanes of northbound I-471 are scheduled to reopen by the end of the year.
Ohio Traffic Impacts and Detour
All access points to I-471 South in Ohio are closed; these include the following restrictions in downtown Cincinnati:
- Liberty Street access to I-471 is closed.
- 5th Street access to I-471 is closed.
- U.S. 50 East and West access to I-471 is closed. (U.S. 50 remains open to thru traffic.)
Southbound I-471 traffic is being detoured by way of I-71 and I-75 South. Thru-traffic motorists and heavy truck (semi) drivers traveling south should use I-275 to I-71/75 to avoid delays, and all HAZMAT operators are required to follow the I-275 outerbelt.
Kentucky Traffic Impacts
A single-lane closure is in effect on I-471 North beginning at the 3.6-mile marker near Memorial Parkway and continuing across the Daniel Carter Beard Bridge.