Streetcar Progress Update - October 19, 2015
Oct 19, 2015
Streetcar Progress Update: October 19, 2015
2nd & Main Street Intersection Remains Closed Oct 11-30 for Final Track Work
Last week, crews welded the last two rails on the Cincinnati Streetcar track at the corner of 2nd and Main. However, work continues as crews pour concrete and perform remaining steps to complete the trackwork. A full closure of the intersection remains in effect through October 30.
Check www.roadmapcincy.com for details on detours and alternative routes.
Block by Block Construction –Oct 19-25, 2015
MAIN STREET:
- At 2nd: stop power work (1 week remaining), new curve track work (2 weeks remaining)
- 2nd to 6th: asphalt paving work (1 week remaining)
- 3rd to 4th: paver and restoration work (2 weeks remaining)
WALNUT STREET:
- 2nd to Central Parkway: OCS wire adjustments (1 week remaining)
- 7th to Central Parkway: traffic signal work (1 week remaining)
- 9th to Central Parkway: underground feeder wires (1 week remaining)
PROGRESS LAST WEEK:
The last track weld at 2nd and Main Streets.
Unit #1 in Elmira going through some inspections.
Interior of Unit #1.