Progress & Updates

Get the latest news on the Cincinnati Streetcar.

July 3, 2014
Video: On The Streets Of Cincy

Watch Episode 1 of "On the Streets of Cincy," bringing you the latest on the road impacts of City construction projects!

June 30, 2014
Streetcar Progress Update: June 30, 2014
Streetcar Progress Update: June 30, 2014

The intersection of 12th & Race streets is closed for 6 weeks as of Monday morning.

June 23, 2014
Streetcar Progress Update: June 23, 2014
Streetcar Progress Update: June 23, 2014

Trackwork affects several intersections along 12th Street this week.

June 16, 2014
Streetcar Progress Update: June 16, 2014
Streetcar Progress Update: June 16, 2014

Construction this week affects Vine Street at 12th Street.

June 9, 2014
Streetcar Progress Update: June 9, 2014
Streetcar Progress Update: June 9, 2014

Westbound 12th Street will be closed 9 a.m. to 4 p.m. weekdays between Race and Elm streets, and between Walnut and Vine streets for trackwork.

June 2, 2014
Streetcar Progress Update: June 2, 2014
Streetcar Progress Update: June 2, 2014

Eastbound Central Parkway will be closed between Vine and Walnut streets later this week for track installation.

May 27, 2014
Streetcar Progress Update: May 27, 2014
Streetcar Progress Update: May 27, 2014

Expect intense construction on Walnut Street in the Central Business District.

May 19, 2014
Streetcar Progress Update: May 19, 2014
Streetcar Progress Update: May 19, 2014

Construction gets underway in earnest for track along 12th Street.

May 12, 2014
Streetcar Progress Update: May 12, 2014
Streetcar Progress Update: May 12, 2014

Concrete crews were finishing the last piece of straight track on Central Parkway before we make the turn down Walnut Street.

May 2, 2014
Streetcar Progress Update: May 2, 2014
Streetcar Progress Update: May 2, 2014

We're up to 7,112 feet of track installed.